Migration wave plan

Template · Published · Source reviewed

Use after Migration assessment. One row per workload (a report family, an ETL flow or a subject area), not per table. The Migration pattern is chosen per row, not for the whole estate.

1. Workload inventory and treatment

ID Workload Legacy components (jobs, procs, reports) Consumers Value (H/M/L) Effort (H/M/L) Treatment Target data product Depends on Wave
WL-01 retire / rehost / replatform / refactor / rebuild

Treatment guide

Treatment Use when
Retire No active consumer in 6 months, or duplicated by another workload. Retire before you migrate
Rehost Lift as-is, for short-lived or low-value workloads you will retire soon
Replatform Convert code with tooling (SnowConvert AI, Lakebridge) into dbt models with minimal redesign
Refactor Logic is sound but the model is not; remodel into medallion layers and data products
Rebuild Logic is unknown or wrong; extract Business rules first, then build from the rules

2. Wave sequencing rules

  1. Wave 0 (foundations): landing zone, identity, network, catalog, CI/CD, one thin end-to-end pipeline.
  2. Wave 1 (pilot): one workload with high value, medium effort, few dependencies and a willing business owner. It proves the playbook.
  3. Later waves group workloads that share sources, so each shared source is ingested once.
  4. Move consumers with their data. Do not leave a report pointing at legacy with its data migrated.
  5. Use the Strangler fig pattern: switch off legacy pieces as each wave exits.

3. Wave register

Wave Workloads Business owner Start Parallel run window Cutover target Legacy decommission date Status
0 Foundations Platform lead n/a n/a
1

4. Entry criteria (per wave)

5. Exit criteria (per wave)

  • [ ] Parallel run completed for the agreed window, with every run reconciled
  • [ ] Reconciliation sign-off by the business owner
  • [ ] Traceability gap report clean: no rule not migrated, none migrated on faith, no undecided suspected defects (Traceability gap report and rule trace card; proposed)
  • [ ] Consumers repointed and confirmed
  • [ ] Legacy jobs disabled, then decommissioned after the agreed hold period
  • [ ] Run cost compared with legacy and recorded
  • [ ] Lessons folded into the playbook

6. Risks and debt log

Risk / debt item Wave Impact Mitigation Owner