Copy one per workload. It is complete when every check below is green for the whole Parallel run window and the business owner has signed. Method detail is in Reconciliation, parallel run and cutover.

1. Scope

Field Value
Workload ID (from Migration wave plan)
Legacy objects
Target objects
Parallel run window e.g. 4 weeks including one month-end
Agreed tolerances exact for counts and keys; e.g. 0.01% for floating-point sums
Known, accepted differences each one with its reason and an approver and, for deliberate rule changes, an accepted decision record id; the pinning test kept

2. Checks (run automatically on every parallel run)

# Level Check Tolerance Result
R1 Table Row count per table and per partition (e.g. per day) exact
R2 Table Primary key set: missing in target, extra in target 0
R3 Column Null count and distinct count per column exact
R4 Column Min/max for numeric and date columns exact
R5 Aggregate Sum of key measures, grouped by business dimensions agreed
R6 Row Hash of each row (normalised types, trimmed strings, UTC timestamps) compared on key 0 mismatches
R7 Sample Random and edge-case records compared field by field 0
R8 Report Top reports / extracts produce identical outputs exact
R9 Rule Each extracted business rule has a passing equivalence test or an accepted decision record (proposed, Tracing rules from legacy code to modern code) all pass
R10 Ops Load completes within SLA; failures alert met

Use Lakebridge reconcile or SnowConvert AI validation where they fit. Otherwise write the checks as dbt tests or a reconciliation job that writes results to a table, so the history is auditable.

Common false differences to normalise before comparing: character padding, collation and case, timestamp time zones and precision, decimal scale, NULL vs empty string, and float rounding.

3. Daily parallel-run log

Date Legacy run ok Target run ok R1-R10 all green Differences found Root cause Fixed in

4. Cutover

  • [ ] All checks green for the whole window, including at least one period-end
  • [ ] Business owner sign-off recorded
  • [ ] Every rule writing to the cut-over tables is verified or waived (proposed, Tracing rules from legacy code to modern code; Traceability gap report and rule trace card G8)
  • [ ] Consumers' connections switched (BI, extracts, APIs, downstream jobs)
  • [ ] Legacy jobs disabled (not deleted) and the legacy store set read-only
  • [ ] Rollback plan tested: how to re-enable legacy within N hours
  • [ ] Monitoring live on the target (Data observability)
  • [ ] Hold period agreed (e.g. 30-90 days), then decommission and archive under the records schedule